A massive power plant is coming to Licking County, creating construction jobs for members of Insulators Local 50.
EdgeConneX, a Virginia-based company, announced it will build a natural gas-fired power plant in Western Licking County called PowerConneX to meet growing electricity demand from Central Ohio data centers.
Powering a New Albany Data Center
The plant will supply electricity to a new data center within the New Albany International Business Park, one of several data centers either operating or proposed in the area. In late February, EdgeConneX notified the Ohio Power Siting Board and local stakeholders that its affiliate, PowerConneX Inc., intends to apply for state permits to construct a 120-megawatt power plant.
The facility is planned for 48.6 acres northwest of S.R. 161 and Mink Street. According to industry standards, a plant of this size could generate enough electricity to power up to 120,000 homes annually. EdgeConneX has developed more than 80 data centers across over 50 markets worldwide. This project marks its first venture in Ohio.
Project Timeline
Construction could begin as early as the fourth quarter of 2025, with commercial operations potentially starting as soon as the first quarter of 2026.
A Growing Need for Power
The project comes as Central Ohio works through a data center construction boom, with the number of data centers in the region growing from just one in 2017 to 105 today. Each new data center adds to the region’s need for electrical generation capacity, and American Electric Power officials predict electricity demand will double in the coming years.
Grid operator PJM’s recent long-term load forecast found there may not be enough electricity to affordably power every home, device or industry connected to the grid as soon as June 2026. Asim Haque, PJM Senior Vice President, told WOSU the region faces a supply crunch driven by the closure of coal-fired power plants. While a shift toward renewable sources like solar and wind is a positive step, he said the grid needs large-scale, stable generation — more nuclear, gas-fired, or coal-fired plants — to maintain reliability.
A 2024 Public Utilities Commission of Ohio rate filing from AEP shows the company has agreements to add 4,400 megawatts of power to Central Ohio by 2030 to meet new customer demand — bringing total regional electricity demand to roughly the level of Manhattan.
This project is what is known as “behind-the-meter,” meaning the power generated will not go to the grid but will instead power a data center directly.
What It Means for Local 50 Members
The PowerConneX plant won’t solve the region’s entire power capacity challenge on its own, but it’s a meaningful step toward moving data centers’ electricity needs off the grid. Plus, it adds another major construction project to the pipeline for mechanical insulators and other skilled trades in the region.
For experienced mechanical insulators, continued investment in power generation infrastructure means ongoing opportunities for Local 50 members – both in the initial construction and ongoing maintenance in the years ahead.
Non-union mechanical insulators who want to work on future “behind-the-meter” power generation projects should visit our Experienced Insulators page to learn more about becoming a member of Local 50.