One Year Into Arsenal-1, Anduril Targets Q2 Production Start

A year after announcing plans for Arsenal-1 in Pickaway County, Anduril Industries says construction is progressing on multiple buildings, and the defense contractor is preparing to begin production of its first aircraft program at the site by the second quarter of 2026.

Construction Progress

In a post on its website, Anduril said construction on Building 1 is well underway. Once complete, the building will include 775,000 square feet of production space, plus 120,000 square feet of office and support space. The company also broke ground on Building 2 last summer, a facility planned at more than 924,000 square feet, where crews are now raising walls and preparing to begin interior work.

Anduril has finalized a full site plan outlining a 10-year buildout through 2035, which includes additional manufacturing and warehouse buildings, a centralized hub, a substation, facilities operations buildings, roadwork, and a campus amenities building. The buildings will come online in a staggered cadence rather than all at once.

The project’s first phase is expected to create 400 construction jobs for the region’s union building trades. Elford is serving as the phase-one general contractor. Anduril is also working with Pickaway County officials and state engineers on road and traffic design, and has begun outreach to community partners and schools across Central Ohio.

Staffing Up

On the staffing side, Anduril has hired its first 25 Ohio employees, who joined the company in July and trained at its California headquarters. Those early hires are in technical production and manufacturing roles and will return to Ohio to support full-scale hiring and the start of production in Building 1. Arsenal-1 remains the largest single job-creation investment in Ohio history, with the company expecting to hire around 4,000 employees overall.

Anduril has also made several leadership hires tied to the Ohio expansion, including Kevin Kerr, Vice President of Production for Arsenal-1; David Frash, Director of State and Local Government Relations; and Kristen Easterday, Director of External Affairs. All will be based in Central Ohio.

First Product: YFQ-44A

The first product slated for Arsenal-1 is YFQ-44A, which Anduril describes as a missionized variant of its Fury autonomous fighter jet, built for the U.S. Air Force’s Collaborative Combat Aircraft (CCA) program. Anduril said it took YFQ-44A from clean-sheet design to a fully built aircraft in 365 days, began flight testing in October, and is working toward operational capability by the end of the decade.

Production of YFQ-44A in Building 1 is set to begin by Q2, with additional programs expected to move production to Arsenal-1 over the following 12 months. Near-term priorities include advancing construction across the initial facilities, expanding hiring and training of Ohio-based employees and standing up manufacturing systems and production operations.

What It Means for Local 50 Members

With two buildings actively under construction and a 10-year site plan mapped out through 2035, Arsenal-1 is shaping up to be one of the longest-running sources of construction work in the Central Ohio region. For experienced mechanical insulators, this one-year update is a good sign that the project — and the opportunities tied to it — are only getting started.

Are you an experienced insulator looking to get in on projects like these? Visit insulators50.com/experienced-insulators to learn how to become a member of Insulators Local 50.