Cologix, a leading data infrastructure provider, has started construction on its newest project — a $1 billion data center in the Lewis Center area. Union trades will be at the heart of the build, continuing to turn Central Ohio into a national data center hub.
Site Details
Site preparation is underway on the 28-acre property at Green Meadows Drive and Home Road in Orange Township. The project, known as COL5, will deliver 120 megawatts of capacity at full build-out and support high-density, ultra-low-latency, sustainable infrastructure. The facility will connect to Cologix’s four other Central Ohio locations.
The first phase — a 60,000-square-foot, single-story facility — is scheduled for completion by fall 2026, with a second building to follow. According to The Columbus Dispatch, that second building will have a site capacity of roughly 95 MW and cover an estimated 75,000 square feet.
A Big Workforce, No Agreement
Roughly 400 union construction workers are expected to work on the project. What sets COL5 apart from other data center megaprojects in the region is that it’s being built without a labor agreement in place — yet building trades members are still expected to make up a large majority of the on-site workforce.
Cologix’s Growing Central Ohio Footprint
COL5 is Denver-based Cologix’s fifth Columbus-area data center since entering the market in 2014, making Central Ohio the company’s largest U.S. location. Nancy Tiemeier, Cologix’s Account Director for Central Ohio, spoke with The Columbus Dispatch about why the company continues to invest here.
“There’s a lot of growth going on,” Tiemeier said. “As far as environment, we don’t get the storms or hurricanes or earthquakes like other parts of the country. It’s also a gateway for network connection between the Midwest and the East Coast.”
Cologix’s four existing Columbus-area centers total 500,000 square feet and 80 megawatts of capacity, making the company the largest colocation provider in Central Ohio. Colocation providers rent out data center space — from individual racks to entire buildings — to other companies that operate their IT systems remotely.
More Growth on the Horizon
Cologix isn’t stopping at COL5. Later this year, work is expected to begin on a $7 billion, 154-acre campus in Johnstown, in western Licking County, that could eventually house up to eight additional data centers.
What It Means for Local 50 Members
Between COL5 and the upcoming Johnstown campus, Cologix is shaping up to be one of the steadiest sources of data center work in the region for years to come. For experienced mechanical insulators, it’s another sign that Central Ohio’s “Silicon Heartland” boom shows no signs of slowing down.